Please see below the latest mast updates, and the expected time they will be offline.
The work for these sites is planned to commence at 8am each day.
Date | Site | Network | Expected Time Offline | Works | Status |
| 7th May 2026 | Mont Felard | Airtel | 10 Hours | Structure & Antenna Swap | Completed |
| 8th May 2026 | Mont Felard | Airtel | 2 Hours | Resolve snag | Completed |
| 9th May 2026 | Kensington Car Park | Sure | 8 Hours | Antenna swap | Completed |
| 10th May 2026 | Kensington Car Park | Sure | 5 Hours | Antenna swap/ Prep work | Completed |
| 11th May 2026 | Beaumont Business Park | Sure & Airtel | 8 Hours | RAN Enabling Work | Pending |
| 12th May 2026 | Beaumont Business Park & Fremont | Sure & Airtel | 8 Hours | RAN Enabling Work | Pending |
| 13th May 2026 | Rondin | Sure & Airtel | 8 Hours | RAN Enabling Work | Pending |
| 14th May 2026 | Rondin | Sure & Airtel | 8 Hours | RAN Enabling Work | Pending |
| 15th May 2026 | Windsor Court | Sure & Airtel | 8 Hours | RAN Enabling Work | Pending |
| 16th May 2026 | Windsor Court | Sure & Airtel | 3 Hours | RAN Enabling Work | Pending |